Hi O'leary's,
We passed our insulation inspection yesterday and we are moving on to drywall and finish carpentry. All of the rough is now complete. We finished the HVAC work yesterday as well and will patch and clean the guest bedroom.
Once the drywall is complete, we will install the bead board ceiling and trim out all of the windows. Here are some progress photos.
This project is a renovation of a 3 season porch in Cohasset, Massachusetts. The home owners would like to convert the space into a usable playroom and TV room for their enjoyment year round. We will be installing new windows, a french door and lots of built-in storage in the form of bookcases and benches.
Thursday, August 9, 2012
Sunday, August 5, 2012
Framing complete
Last week was a great week. We finished both the rough electric and rough framing of the porch. The new stairs came out perfect and match the existing. We are ready for sign off and will get that on monday. We also completely painted the exterior wood work and stained the decking. Things are really coming together on the exterior.
Next week we will start by focusing in the interior. We will be completing the air conditioning duct work, begin to insulate the walls and ceiling and start to do the drywall. Should be a good week. Here are some pictures, enjoy.
Next week we will start by focusing in the interior. We will be completing the air conditioning duct work, begin to insulate the walls and ceiling and start to do the drywall. Should be a good week. Here are some pictures, enjoy.